In this article, we explain how to override service package hours when allocating duties.

L
Written by Lucy Robbie
Updated over a week ago

If trying to allocate a duty which results in the number of hours exceeding the service package hours, if the planning rule has been set to Enforce, the duty opens and displays a failed planning rule warning message.

To view this message, follow these steps.

  1. Click Rostering, then click Visit.

  2. Click Planning, then locate the relevant visit.

  3. Double-click on the visit.

  4. Under the Employee section, you'll see any errors here.

  5. Select the override option if required.

  6. Add a note if the Mandatory Notes option has been selected.

  7. Click Save.